Silt from construction silting the drain

Tejgaon, industrial lane

Run-off from a washing plant is carrying silt straight into the drain. The bed has risen by about half a metre and the lane floods on a short shower.

Time from report to resolution

13 days 7hfiled 24 Sept 2026 · resolved 7 Oct 2026

The clock ran from the moment a resident filed this to the moment the department marked it resolved.

Progress

  1. Reported24 Sept 2026 · 09:30
  2. Acknowledged25 Sept 2026 · 10:00

    WASA drainage zone

    Plant directed to install a settling tank.

  3. Work in Progress30 Sept 2026 · 08:00

    WASA drainage zone

    Settling tank built; drain desilted.

  4. Resolved7 Oct 2026 · 16:00

    WASA drainage zone

    Flow restored. Plant inspected for compliance.

Department’s statement

Response from Dhaka WASA

Required a settling tank at the plant and desilted the drain. Compliance to be re-checked in three months.

Same category

Also on this desk

Drainage channel filled with construction waste

Uttara Sector 7, channel beside the schoolWard 1, Uttara Sector 7

Drainage & WaterloggingMedium priority189 people have flagged this
DHK-2026-0143Work in Progress10 days 3h waitingOver a week