DHK-2026-0143Work in ProgressMedium priority

Drainage channel filled with construction waste

Uttara Sector 7, channel beside the school

Builders have been tipping broken concrete and sand into the open channel for months. It is now about a third full and the section no longer drains.

Time from report to resolution

10 days 3hand counting — filed 9 Oct 2026

The clock started when this was filed and stops when the department marks it resolved. It is currently at the "Work in Progress" stage.

Progress

  1. Reported9 Oct 2026 · 10:45
  2. Acknowledged10 Oct 2026 · 09:00

    WASA drainage zone

    Illegal dumping confirmed. Cases filed against two builders.

  3. Work in Progress15 Oct 2026 · 11:00

    WASA drainage zone

    Channel being cleared by excavator; 40 cubic metres removed.

Still open

This report is at the Work in Progress stage. The next step is Resolved. Nothing has been marked resolved, so the clock is still running.